The Challenges

Rather than spend high dollars on a system upgrade, many food plants opt for a temporary solution to solve their HVAC problems. In many instances, the HVAC system is doing its job but fails to deliver ideal conditions during the extreme heat of the summer months. In this case, a food processing facility in the Gulf Coast knew that hot, humid weather was coming and they contacted DRYCO for a temporary cooling solution. Working alongside the facility engineers, DRYCO delivered and set up the temporary air conditioning unit, including the ductwork and interior layflat (temporary ducting system).

Project Details

Client:Mechanical Contractor
Location:Mississippi
Year Completed:2015

Equipment Used

  • 80 Ton Air Conditioning Unit